Explainer
EMD, security deposit, PBG and retention: money across the tender lifecycle
The short answer
EMD secures your bid and comes back, or is adjusted, at award. Performance security, often called PBG or security deposit, secures the contract until warranty or defect liability ends. Works contracts may also withhold retention money from running bills. Each can usually be a demand draft, bank guarantee, e-BG, online payment or insurance surety bond.
Key takeaways
- In the government procurement manuals, "security deposit" can mean the performance security itself or a separate retention withheld from running bills, so check which one your contract means.
- Performance security under the current central manuals is 3 to 5 percent of contract value for goods and 3 to 10 percent for works, as the tender specifies.
- In works, retention is commonly 5 percent of each running bill, released half at taking over and half after the defect liability period.
- Insurance surety bonds and e-bank guarantees became accepted forms through 2022 amendments, while corporate guarantees and indemnity bonds are not accepted.
- Plan cash and bank limits for the whole contract, because EMD, PBG and retention can overlap for many months.
Why "security deposit" means two different things
Our EMD in tender guide defines each payment and compares them side by side. This one follows the money through time instead: what the buyer holds from you at each stage of a contract, in what form, and when it should come back.
Start with the term that causes most of the confusion. The Department of Expenditure's Manual for Procurement of Goods, 2024 (opens in a new tab) describes performance security as "(or Performance Bank Guarantee (PBG) or Security Deposit (SD))". In many goods tenders, then, security deposit and PBG are one thing under two names.
Works contracts add a second, separate deposit. The Manual for Procurement of Works, 2025 (opens in a new tab) says that, in addition to performance security, works contracts usually withhold a percentage of each running bill as "Security Deposit/ retention money" until final acceptance. When a civil contractor complains about SD, this deduction is often what they mean.
So the honest answer to "what is the difference between EMD and security deposit" starts with a question back: which security deposit? Read the definitions clause and the conditions of contract before you price.
At the bid stage: what you put at risk before award
Before award, the only thing at stake is your bid security: an EMD, or a bid securing declaration where the tender allows one. It sits with the buyer through the bid validity period and must stay valid for the extra period the tender sets.
Two things can stretch this stage. Evaluation may run past the validity period, and the buyer may ask bidders to extend both the bid and the bid security. The Goods Manual says a bidder may refuse that request without forfeiting its bid security, and those who agree must not change their bids. Each extension also means amending a bank guarantee or keeping cash locked longer.
The other is a two-packet tender in which you are knocked out at the technical stage. Your EMD should then come back well before the price bids are settled. The due dates for each case are in our EMD refund process guide.
At award: EMD converts or comes back, and the PBG goes in
Award is where the money changes shape. The winner furnishes performance security by a date in the tender, which the manuals put at generally 14 to 28 days after notification of award. The current manuals, following a Department of Expenditure OM effective 1 January 2024, set it at 3 to 5 percent of contract value for goods and 3 to 10 percent for works, with the exact figure in the tender. Older tender templates still carry older percentages, so read your own.
What happens to the winner's EMD depends on the tender. The Goods Manual says it is refunded on receipt of performance security, or adjusted against the security deposit as the tender provides. A GeM-hosted RFP from IIFCL in 2026 takes the second route: "EMD of successful bidder will be retained as Performance Security and the amount would be reduced from the performance security amount to be submitted" (IIFCL RFP (opens in a new tab)). The manual's model award letter even tells the supplier to "apply for a refund of EMD deposited over and above the SD, if any".
Miss the performance security deadline and the award can be treated as a withdrawal of your offer. The Goods Manual then allows forfeiture of the EMD and action such as deregistration and debarment. A late PBG is one of the costliest mistakes a winning bidder can make, so line up your bank before the result, not after it.
During execution: retention money from running bills
In works contracts, each running bill is paid net of a retention deduction, which the Works Manual describes as usually five percent of each bill, until it reaches a limit set in the contract. The manual also notes that the EMD, instead of being released, may form part of this security deposit.
The contractor can swap cash for paper. Under para 5.1.3, it may replace the retention with an unconditional bank guarantee or insurance surety bond at two points: when the deduction reaches half the retention limit, and when it reaches the full limit. That frees working capital in the middle of the job, at the cost of bank limits or a premium.
Goods contracts work differently. The Goods Manual says that, unlike works, taking part of the performance guarantee as money retained from the first or progressive bills is not acceptable in goods procurement. If a goods tender proposes bill deductions as security, ask about it in a pre-bid query.
Defect liability and release: when the PBG and retention come back
The performance security must stay valid for 60 days, or whatever period the tender states, beyond completion of all contractual obligations, including the defect liability or warranty period. It should be refunded without interest once all obligations are complete, and not later than 60 days after the defect liability or warranty period ends.
Retention comes back in two halves under the Works Manual. One half is released when the taking-over certificate is issued, in proportion where sections are taken over separately. The other half is released 60 days after the defect liability period ends or after final payment, whichever is earlier, on the engineer's certificate. Where parts of the work carry different defect liability periods, the latest one governs.
Long supply contracts have a useful provision. For rate contracts and other multi-year goods contracts, the Goods Manual lets buyers reduce performance security in proportion to the balance contract period instead of holding the full amount throughout. It is not automatic, so ask for it.
| Stage | Security held | Usual basis | When it should come back |
|---|---|---|---|
| Bid submission to award | EMD or bid securing declaration | Amount fixed in the NIT | Unsuccessful bidders: soon after validity ends; winner: on PBG, or adjusted |
| Award to contract signing | Performance security (PBG or SD) | 3 to 5 percent of contract value for goods, 3 to 10 percent for works, per tender | Stays in place through execution |
| Execution (works) | Retention from running bills | Usually 5 percent of each bill, up to a contract limit | Half on the taking-over certificate |
| Defect liability or warranty | Performance security and the rest of the retention | As above | PBG within 60 days after the period ends; retention 60 days after the period or final payment, whichever is earlier |
| Low bids, where the buyer's rules use it | Additional performance security | Set by the buyer's rules and the tender | As the tender provides |
Release is where many contractors wait longest. LiveLaw reported one Delhi High Court ruling under the headline "Employer Cannot Retain Performance Bank Guarantee After Acknowledging Of Due Performance (opens in a new tab)". Courts are a slow route, though. A completion certificate and a dated release request on file usually work sooner.
DD, FDR, BG, e-BG or surety bond: which form should you use?
The central manuals accept insurance surety bonds, account payee demand drafts, bank guarantees including e-bank guarantees, and online payment for both bid and performance security, with banker's cheques also listed for bid security. Fixed deposit receipts still appear in many tenders. Corporate guarantees and indemnity bonds are not accepted for either.
| Form | What it ties up | How it is released | Points to check |
|---|---|---|---|
| Demand draft or banker's cheque | Cash, from the day you buy it | Instrument returned, or refund by transfer | A DD returned after its validity needs your bank to revalidate or cancel it |
| Fixed deposit receipt (FDR) | Cash, though the deposit keeps earning interest | Buyer discharges its lien | Lien in the buyer's favor, in the tender's format |
| Bank guarantee | Your non-fund limit, often with margin or collateral | Original returned, or a written release | Issued or confirmed by an acceptable bank; for works, a BG merely advised by a bank is not acceptable |
| e-bank guarantee | The same as a bank guarantee | Buyer releases it on the NeSL platform | The buyer's unique identity number and email must be in the tender |
| Insurance surety bond | A premium; the manual says no collateral deposit is required | Written discharge by the beneficiary | Whether the tender lists surety bonds at all |
| Online payment | Cash | Refund to the paying account | Keep the UTR and pay from the bidder's own account |
Insurance surety bonds were added to GFR Rules 170 and 171 by a Department of Expenditure OM of 2 February 2022, and e-bank guarantees by an OM of 5 August 2022. The Goods Manual describes the surety bond as a three-party arrangement in which the insurer pays if the principal does not, and says that, unlike a bank guarantee, it "does not require a deposit of a collateral amount". The Works Manual also lets buyers allow contractors to replace existing bank guarantees with surety bonds or e-BGs in running contracts, as long as the new security arrives before the old one is released.
Your choice depends on what is scarce. A firm with idle cash may prefer an FDR that keeps earning. A firm with tight bank limits may find a surety bond worth the premium, where the buyer accepts it. A firm bidding often may prefer e-BGs, because the manual notes how easily they can be verified, which removes one cause of delay at bid opening.
Illustrative example: one works contract, from bid to final release
A Bhopal contractor bids for Rs 2.4 crore of drainage and boundary wall works at a central institute. Here is how the security moves over two years.
- Bid: EMD of Rs 4,80,000 (2 percent, rounded to the nearest thousand) is paid online.
- Award: the contractor wins. The tender says the EMD forms part of the security deposit, so it is not refunded.
- Within 21 days: a performance security of 5 percent, Rs 12,00,000, is furnished as an e-BG valid to 60 days beyond the defect liability period.
- Months 1 to 10: each running bill loses 5 percent to retention, toward a contract limit of Rs 12,00,000 that includes the EMD. At Rs 6,00,000, the contractor replaces the cash retention with a bank guarantee.
- Month 11: the taking-over certificate is issued and half the retention is released.
- Month 23 plus 60 days: the 12-month defect liability period has ended, so the other half of the retention and the e-BG are due for release.
How to plan cash and bank limits across the contract
These securities overlap. Retention builds up while the PBG is live, and a slow EMD refund on another tender can sit on top of both. Contractors who plan only for the EMD often find the real cost around month six.
- Price the cost of security into the bid: guarantee commission or surety premium for the full validity, plus the interest cost of cash held back.
- Ask in pre-bid queries whether surety bonds and e-BGs are accepted, and whether retention can be replaced by a guarantee.
- Track the expiry and claim period of every guarantee. The manuals tell buyers to review each month the guarantees expiring in the next three months; run the same review on your side.
- Expect the buyer to keep the original guarantee while it is extended. The manuals say a guarantee should never be handed to the contractor for extension, so ask your bank to send the amendment directly.
- File completion and taking-over certificates as soon as they are issued, because they start the release clocks.
Some buyers ask for extra security when a bid is far below the estimate; see additional performance security. For guarantee formats, claim periods and invocation, see our performance bank guarantee guide. MSE registration does not reduce any of these: the Ministry of MSME's FAQ on the procurement Order (opens in a new tab) says the Policy gives no exemption from security deposit or PBG. Its EMD exemption is covered in EMD exemption for MSMEs.
How AI tools help track security clauses, and what finance decides
Security terms are scattered: EMD in the NIT, performance security in the conditions of contract, retention in the special conditions and release in the defect liability clause. TenderGenie Document Intelligence pulls requirements and clauses from the full tender pack, each with a reference to its source page, so finance sees every security term before pricing.
In TenderGenie, obligation mapping in Risk & Compliance shows which clauses create obligations, linked to the source clause, and risk flags carry an impact and a recommended action for the reviewer to accept, change or reject.
People decide the rest: which instrument to use, how much security cost to build into the price, whether the release terms are acceptable, and whether the contract is worth the capital it ties up. Those questions belong in a proper bid/no-bid decision.
Questions and answers
Is security deposit the same as performance security?
Often, yes. The Department of Expenditure's procurement manuals treat performance security, performance bank guarantee and security deposit as names for the same contract security. Works contracts may also hold a separate security deposit, usually called retention money, deducted from each running bill. The tender's definitions and conditions of contract tell you which one a document means.
What is the difference between EMD and PBG?
EMD is bid security. It protects the buyer against a bidder withdrawing or refusing to sign, and its job ends at award. A PBG is performance security. The winning bidder gives it after award, and it protects the buyer until all obligations, including warranty or defect liability, are complete. The winner's EMD is then returned or adjusted, as the tender says.
Is EMD adjusted against security deposit?
It can be, if the tender says so. The Goods Manual allows the successful bidder's EMD to be refunded on receipt of performance security or adjusted against the security deposit under the tender terms, and the Works Manual says EMD may form part of the security deposit. When it is adjusted, you furnish only the balance.
What is retention money in construction contracts?
Retention money is a share of each running bill, usually five percent under the Works Manual, that the buyer holds back as security until final acceptance, up to a limit set in the contract. Half is normally released at taking over and the rest after the defect liability period. The contractor may replace it with a bank guarantee or surety bond at stated points.
When is the performance bank guarantee released?
Under the Department of Expenditure manuals, it should be refunded without interest once the contractor has completed all obligations, and not later than 60 days after the warranty or defect liability period ends, unless the tender sets another period. Keep the completion certificate and write for release as soon as the period ends.
Can an insurance surety bond be used instead of a bank guarantee in tenders?
Yes, where the tender allows it. A Department of Expenditure OM of 2 February 2022 added insurance surety bonds to the accepted forms of bid security and performance security under GFR 2017. Many central tenders now list them, but some state and PSU tenders still accept only bank guarantees, demand drafts or online payment, so check the tender.
Is an e-bank guarantee accepted in government tenders?
Central rules accept it. A Department of Expenditure OM of 5 August 2022 added e-bank guarantees, which are issued and verified on the NeSL platform. The buyer gives its unique identity number and email in the tender so your bank can create the e-BG in its favor. Check the tender for any format it prescribes.
How much is security deposit in government tenders?
Performance security under the current central manuals is 3 to 5 percent of contract value for goods and 3 to 10 percent for works, as the tender specifies. Works contracts may add retention of around five percent of each running bill, up to a limit in the contract. State and PSU rules differ, so the figure in your tender is the one that counts.
Sources
- Department of Expenditure: Manual for Procurement of Goods, Second Edition 2024 (opens in a new tab)
- Department of Expenditure: Manual for Procurement of Works, Second Edition 2025 (opens in a new tab)
- General Financial Rules 2017 (Department of Expenditure; copy hosted by ICAR) (opens in a new tab)
- IIFCL RFP on GeM (March 2026) with EMD retained as performance security (opens in a new tab)
- LiveLaw: Delhi High Court on retaining a performance bank guarantee (opens in a new tab)
- Ministry of MSME (DC-MSME): FAQs on Public Procurement Policy for MSEs Order 2012, dated 27 January 2022 (opens in a new tab)
Rules and portal steps change. Check the current tender document and the buyer's portal before you rely on any figure here.
Next steps
Where TenderGenie helps with this
Document Intelligence
Turn a complex tender pack into requirements your team can understand and review.
Explore solutionRisk & Compliance
Make qualification and risk visible before committing time and resources.
Explore solutionRelated insights
See it on your tender
Bring a tender
your team is working on.
We will walk through TenderGenie using the kind of tender documents your team handles, with your reviewers in control of every decision.