Go/no-go decision for tenders: a scorecard for Indian bids

By TenderGenie Editorial TeamUpdated 10 min read

The short answer

A go/no-go decision is the recorded choice to bid for a tender or walk away. Run knock-out checks first: eligibility, mandatory registrations, approved-vendor status and time to prepare. If the tender survives, score it on a weighted bid/no-bid matrix out of 100. Bid at 70 or more, review 50 to 69 with conditions, and decline below 50.

Key takeaways

  • Knock-out checks come before any scoring, because one failed eligibility condition makes every other strength irrelevant.
  • A weighted scorecard with seven criteria turns a gut feeling into a number that the whole team can argue about openly.
  • Treat 70 and 50 as starting thresholds, and let any single criterion scored 1 force a discussion even when the total looks healthy.
  • Decide twice: a quick gate within two working days of download, and a final gate after pre-bid replies and corrigenda.
  • Write down the reasons for every no-bid, so the next team does not repeat the same three weeks of work on a similar tender.

What is a go/no-go decision in a tender?

Go/no-go and bid/no-bid mean the same thing: before your team spends real effort on a response, someone decides whether this tender is worth winning and whether you can win it. In Indian public tenders the cost of getting this wrong is not only the bid team's time. EMD gets blocked, engineers stop estimating live orders, and a won tender with bad terms can hurt more than a lost one.

Most teams already make this call. The trouble is that they make it by mood. The sales head likes the buyer, the tender looks big, and three weeks later someone notices the turnover criterion. A startup advice site puts it bluntly: "Chasing a tender you're structurally ineligible for is the most common wasted month in govt sales." A written scorecard is the cheapest fix for that.

When should you make the bid/no-bid decision?

Use two gates. Each one has a different job.

  1. Gate 1, within two working days of downloading the tender: run the knock-out checks and a rough score. Most tenders should die here, cheaply.
  2. Gate 2, after the pre-bid replies and any corrigendum: score again with the final terms. Replies often change payment terms, liquidated damages or the delivery period, and that can flip a decision either way.

Between the gates, only the work needed to answer open questions should start: pre-bid queries, a rough cost estimate, a call to the OEM for authorization. Full estimation and document preparation wait for gate 2.

Knock-out criteria: the checks that end the discussion

A knock-out is a condition you cannot meet before the bid due date. If one applies, the answer is no-bid regardless of how attractive the rest looks. Read these clauses first.

Common knock-outs in Indian tenders and whether they can be fixed in time
Knock-outWhere it sits in the tenderCan you fix it before the due date?
Turnover, similar work or bid capacity below the qualifying figureEligibility or PQ criteriaRarely. A JV or consortium helps only if the tender allows one
Not on the buyer's approved vendor list, or no OEM authorization where one is requiredVendor list or approved makes clauseUsually not within one tender cycle
Product local content below the Class-I level where only Class-I local suppliers may bidMake in India clauseNot without changing the product or its sourcing
You or your technology partner is linked to a land-border country and not registeredLand border declarationNo. Registration needs political and security clearance
Item reserved for MSEs and you are not a micro or small enterpriseEligibility clause or reserved item listNo
A mandatory licence, type test or approval you do not holdTechnical specificationSometimes, if the test or approval lead time fits
Too little time to prepare a compliant bid alongside live workNIT datesAsk for an extension in the pre-bid meeting; otherwise no

Two cautions. First, check relaxations before you call something a knock-out: central buyers may relax prior turnover and prior experience for micro and small enterprises, subject to quality and technical specifications, and startups recognised by DPIIT get similar relaxations. Second, read the definitions. "Similar work" and "completed" are often narrower than the sales team assumes. Our guides to pre-qualification criteria, Make in India local suppliers and the land border clause cover each check in detail.

A bid/no-bid matrix you can copy

If the tender clears the knock-outs, score it on seven criteria. Each criterion gets a score from 1 to 5, multiplied by its weight. Add the products and divide by 5, and you have a score out of 100. The weights below suit most manufacturers and contractors bidding for public sector work; change them once and then keep them stable, or the scores stop being comparable.

Weighted bid/no-bid scorecard (weights total 100)
CriterionWeightA score of 1 looks likeA score of 5 looks like
Fit with what you make or build15Outside your core range, a one-off itemCore product or work type you want more of
Technical compliance20Several deviations the buyer is unlikely to acceptFull compliance with proven, type-tested designs
Commercial terms and risk15Uncapped liability, heavy LD, payment 90 days after receiptCapped LD, standard security, milestone payments
Price position and competition15Many regular bidders and recent L1 prices below your costFew qualified bidders and award prices you can match
Customer and payment history10New buyer with a slow-payment reputationRepeat buyer that pays on time
Capacity to bid and deliver15Bid team stretched and shop loaded through the delivery windowPeople and capacity free for both
Margin and cash flow10Thin margin after EMD, PBG and working capital costHealthy margin with manageable cash locked up

Score each criterion against evidence, not hope. Price position should come from award results for similar tenders, not from what the buyer paid five years ago. Commercial risk should come from the actual clauses: read the liquidated damages clause and the payment terms before you score, and look for the clauses that hide in annexures.

Go/no-go thresholds: what score is enough?

  • 70 or more: go. Start full preparation after gate 2 confirms the terms.
  • 50 to 69: conditional. Name the condition in writing, such as "bid if the pre-bid reply caps LD at 10 percent", and decide again when the answer arrives.
  • Below 50: no-bid. Record the reasons and move on.

Totals can hide a fatal weakness, so add one override: any criterion scored 1 triggers a discussion with the approver, whatever the total. A construction publisher in the US suggests a similar red-flag rule: three or more red flags means no-bid, and one or two means a conversation about whether the risk can be reduced or the profit justifies it.

Illustrative example: a transformer maker and an EPC contractor score their tenders

A Vadodara maker of distribution transformers looks at a state power distribution company's tender for 120 units of 250 kVA, worth about ₹5.4 crore. It holds the BIS licence, its type test reports are within the required validity, and its turnover clears the PQ figure. A Pune EPC contractor looks at a ₹186 crore water treatment plant and pipeline package from a municipal corporation. It meets the similar-work and bid capacity criteria. Both tenders pass the knock-outs, so both get scored.

Scores out of 5 (weight in brackets); total = sum of weight x score, divided by 5
Criterion (weight)Transformer makerEPC contractor
Fit (15)54
Technical compliance (20)44
Commercial terms and risk (15)2: payment 90 days after receipt1: uncapped performance liability, no price variation over 30 months
Price position and competition (15)32: seven bidders on the last two similar awards
Customer and payment history (10)2: known delays3
Capacity (15)42: two large bids due the same fortnight
Margin and cash flow (10)32
Total out of 10068: conditional53: conditional, with a score of 1

The transformer maker sets its condition as "bid if the payment cost is priced in". It adds the cost of carrying 90 days of receivables to its price, raises a pre-bid query asking for milestone payment, and bids. The EPC contractor's condition is sharper: "bid only if the pre-bid reply adds a price variation clause". The reply declines. With a score of 1 still sitting on commercial risk, the director calls no-bid, and the reasons go on record for the next tender from this corporation.

Notice what the scorecard did. Neither decision was obvious from the tender value or the buyer's name. Both came from writing down a condition and checking it against a real answer. For EPC teams, our EPC industry page shows how package-level reviews fit together.

Who should make the go/no-go call?

One person owns the scorecard; several people feed it; one person signs. A workable split for a mid-sized manufacturer or contractor looks like this:

  • Bid manager: runs the knock-out checks, collects the scores, keeps the record and chases the open questions.
  • Sales or business development: fit, customer history and what is known about competitors.
  • Engineering or estimation: technical compliance, deviations and a rough cost.
  • Finance: EMD, performance security, payment terms and the working capital the order will lock up.
  • Production or projects: whether the shop or site team can deliver in the delivery window.
  • Legal, for large or EPC contracts: liability, indemnity and LD wording.
  • Approver: set by value bands. For example, a business head up to ₹2 crore and a director above it. Pick bands that suit your size.

Scoring together in one 30-minute meeting works better than collecting scores by email, because the disagreements are the useful part. When engineering scores compliance at 2 and sales scores fit at 5, that conversation is the decision.

How AI tools help with go/no-go decisions, and what your team decides

Most of the time in a go/no-go review goes into finding the evidence: the PQ clause on page 14, the LD clause in an annexure, the last three award prices. TenderGenie's Risk & Compliance compares TQ/PQ criteria with your organization's credentials and documents, maps obligations to their source clauses and flags risks by category, each with its impact and a recommended action. Competitor Intelligence adds award history and frequent bidders, and lessons recorded on earlier tenders for the same customer sit in Enterprise Memory.

The scores, the thresholds and the final call stay with your people. If you want to see how the evidence and the recorded decision come together in one tender workspace, the next step is our bid/no-bid decisions use case for TenderGenie.

Questions and answers

What is go no go decision in tender?

It is the decision, made before serious work starts, on whether to bid for a tender or let it go. A good one checks knock-out conditions such as eligibility and mandatory registrations first, then scores the tender on fit, technical compliance, commercial risk, competition, customer history, capacity and margin. The decision and its reasons are written down so the next similar tender is quicker to judge.

What is bid no bid decision?

It is another name for the go/no-go decision. The bid manager gathers evidence from the tender and from the team, scores the opportunity against agreed criteria, and an approver decides to bid, bid with conditions, or decline. Making it early protects EMD, engineering time and bid team capacity for tenders you can actually win.

What is a bid no bid matrix?

A table of weighted criteria used to score a tender. A common version has seven criteria with weights adding up to 100, each scored from 1 to 5. Multiply each score by its weight, add the results and divide by 5 to get a score out of 100. The matrix makes the reasoning visible and lets you compare tenders over time.

What score should a tender get before we bid?

A practical starting point is 70 or more to bid, 50 to 69 to bid only if a named condition is met, and below 50 to decline. Also treat any single criterion scored 1 as a reason to discuss the tender, whatever the total. Recalibrate the thresholds after about 15 decisions by comparing scores with actual results.

Who should make the go/no-go decision for a tender?

The bid manager should own the scorecard and the record, with input from sales, engineering, finance, production and, for large contracts, legal. The final approval should sit with a named person chosen by tender value, such as a business head for smaller tenders and a director for larger ones. Scoring together in one short meeting usually works best.

When should we decide not to bid for a tender?

Decline when a knock-out applies, such as failing the turnover or similar-work criterion, not being on a required vendor list, or lacking a mandatory approval. Also decline when the weighted score falls below your threshold, or when a condition you set at the first gate, such as a cap on liquidated damages, is refused in the pre-bid replies.

Sources

  1. Ministry of Finance, Department of Expenditure: Manual for Procurement of Consultancy Services, Second Edition 2025 (Make in India classes, land border registration, MSE relaxations), copy hosted by StaffNews (opens in a new tab)
  2. Office of the DC (MSME): Revised FAQs on the Public Procurement Policy for MSEs Order 2012, 25 March 2022, copy hosted by Cochin Shipyard (opens in a new tab)
  3. ConstructConnect: Bid or no-bid, how contractors choose which projects to pursue (June 2026) (opens in a new tab)
  4. echai.ventures: The tender asks for three years of turnover and past government experience (startup guidance) (opens in a new tab)

Rules and portal steps change. Check the current tender document and the buyer's portal before you rely on any figure here.

See it on your tender

Bring a tender
your team is working on.

We will walk through TenderGenie using the kind of tender documents your team handles, with your reviewers in control of every decision.