Guide

NHAI tenders and results: where to find them and how to read them

By TenderGenie Editorial TeamUpdated 9 min read

The short answer

NHAI tenders are published on the central e-tendering portal (etenders.gov.in), where NHAI is listed as an organization, and are also referenced on nhai.gov.in. They cover highway works under EPC, hybrid annuity (HAM), BOT and TOT, toll plaza fee collection and consultancy. Results appear on the same portal under tender status and award of contract.

Key takeaways

  • Find NHAI tenders on etenders.gov.in by opening the NHAI organization listing, then read the full RFP, not the notice.
  • The contract mode (EPC, HAM, BOT, TOT, toll collection or consultancy) decides what you price and what risk you carry.
  • Bid capacity and technical capacity are pass or fail gates in highway tenders, so calculate both before anyone starts pricing.
  • Toll plaza tenders run the opposite way to works tenders: the bidder offering NHAI the highest remittance is usually selected.
  • For results, track each tender by its Tender ID on the portal; news reports and aggregator pages are secondary.

What is an NHAI tender?

The National Highways Authority of India (NHAI) builds, maintains and operates national highways for the Ministry of Road Transport and Highways (MoRTH). An NHAI tender is how it buys that work: new four-lane and six-lane corridors, bypasses, bridges, maintenance, toll collection and the engineers who supervise all of it.

The search phrase "nhai tender" usually hides three different questions. A contractor wants to know which packages are open. A toll operator wants the next fee collection contract. A consultant wants the next supervision or project report assignment. They all start at the same portal but read very different documents.

NHAI is a central buyer, so its tenders do not sit on state portals. If you are new to the overall sequence from notice to award, the tendering process explains it; this guide sticks to what is particular about highway tenders.

Types of NHAI tenders: EPC, HAM, BOT, TOT, toll plaza and consultancy

Before you open the price schedule, find the contract mode on the first page of the RFP. It tells you who pays for construction, who carries traffic risk, and what number you are actually bidding.

NHAI procurement modes in brief (general description; each RFP and model agreement sets the actual terms)
ModeWho funds constructionWho carries traffic riskWhat you bidWho usually bids
EPC (engineering, procurement and construction)NHAI pays the contractor in stagesNHAIA contract price for design and constructionRoad contractors, alone or in joint venture
HAM (hybrid annuity model)Shared: part paid during construction, the rest as annuities over the operation periodNHAIProject cost and related annuity termsDevelopers with construction capability and balance sheet
BOT (toll)The concessionaireThe concessionaireConcession terms such as grant or premiumInfrastructure developers
TOT (toll, operate, transfer)Road already built; the bidder pays an upfront amountThe concessionaireAn upfront payment for toll rights on existing stretchesInvestors and road operators
Toll plaza fee collectionNot applicableThe fee collection agency, through its committed remittanceThe amount you will remit to NHAIUser fee collection agencies
ConsultancyNot applicableNot applicableTechnical proposal plus feeEngineering consultants for supervision, project reports and audits

EPC is the easiest to read if you have done state PWD works: you price the job and get paid as you build. HAM adds financing and operation obligations, so the RFP asks more about net worth. BOT and TOT are investment decisions as much as construction ones, and most small contractors meet them only as subcontractors to the concessionaire.

Where to find NHAI tenders and tender details

NHAI publishes its tenders on the central government eProcurement system at etenders.gov.in (opens in a new tab). Open "Tenders by Organisation" and pick National Highways Authority of India. On 29 October 2026 that listing showed 430 tenders, which tells you how much is moving at any time. The NHAI website also carries tender information, but bids go through the portal.

  1. Search the NHAI listing by keyword (the highway number, the state or the town names in the package) and note the Tender ID. Every later search, corrigendum and result hangs on that ID.
  2. Open the tender details page. It shows the reference number, the closing date, the tender fee and bid security, and the documents to download.
  3. Download the full set: the notice, the RFP, the draft agreement, the schedules and every corrigendum. The notice is a summary; the RFP is what NHAI evaluates against.
  4. Enroll as a bidder on the portal and register your digital signature certificate well before the closing week. Read the RFP for any NHAI-specific registration step it names.
  5. Pay the tender document fee and arrange the bid security in the form the RFP allows. Recent NHAI notices ask for the document fee online only.

Regional offices (the RO in the reference number) and project implementation units issue many smaller tenders: maintenance, repairs, wayside amenities and fee collection. Search by the region as well as by highway, or you will miss them. For how central, state and railway portals fit together, see government tender websites in India.

How to check NHAI tender results

People search "nhai tender result today" hoping for one daily list. There isn't one. Results are recorded tender by tender, so you track each package by its Tender ID.

  • Tenders Status on etenders.gov.in shows where a tender has reached: bid opening, technical evaluation, financial opening or award.
  • Results of Tenders lets you search by Tender ID or keyword (it matches the title and reference number) after a captcha. Each row shows the award of contract (AOC) date and a link to the AOC details.
  • The opening summaries on the portal list who bid and, after financial opening, the quoted figures. This is where you learn your rank and your competitors' prices.
  • Trade news and aggregator sites often report technically qualified bidders on large packages. Treat them as a prompt to check the portal, not as the record.

Results are worth more than curiosity. Over a year they show you who wins in your states, how far below the estimate they bid, and which packages attract few bidders. Keep them in one sheet with the estimate, the L1 price and the number of bids.

Bid capacity and technical capacity in highway tenders

Highway RFPs filter bidders with two tests that many first-time bidders underestimate. Both come from the MoRTH model documents, adapted in each RFP.

Available bid capacity asks whether you can take on this work on top of what you already hold. The usual form is A x N x M minus B. A is your highest or average annual construction turnover over a recent period, updated to current prices by the factors in the RFP. N is the construction period in years. M is a multiplier set in the RFP. B is the value of work you already have in hand. If the result is below the estimated project cost, the bid fails, however good your price.

Technical capacity asks whether you have done similar work at this scale. RFPs typically accept one, two or three completed similar works, with the threshold per work falling as the number of works rises, and they define "similar" carefully: highways, bridges, a minimum length or a category of project. Some RFPs also count payments received on eligible projects over the last five years.

HAM and BOT RFPs add financial capacity, usually a minimum net worth as a share of the project cost. Joint venture rules then decide how each partner's turnover, experience and net worth are combined, and the lead partner often has to meet a larger share.

Toll plaza tenders: how user fee collection contracts work

A toll plaza tender is NHAI hiring an agency to collect user fee at a plaza it operates itself. You don't quote a cost. You quote what you will hand over to NHAI, and you keep the difference between what the plaza collects and what you remit, after your own staff and running costs.

An older NHAI RFP for the Tundla toll plaza (opens in a new tab) (2013) shows the structure. It stated an annual potential collection for the plaza, asked bidders to quote an annual remittance payable weekly, and selected the highest bidder. Bid security was 1% of the annual potential collection, performance security included one month's remittance, and the contract ran for one year or until a new operator took over.

Current fee collection tenders are often shorter, sometimes a few months, and terms change, so treat that 2013 document as a guide to the logic, not to today's numbers. The risks are the same as ever: traffic falling below the estimate, exempt vehicles, electronic toll collection shares, and penalties for late remittance.

Illustrative example: checking bid capacity on an EPC package

A road contractor based in Raipur looks at an NHAI EPC package to four-lane a 24 km stretch, estimated at Rs 350 crore with a 24-month construction period. Its estimator runs the capacity check before anyone opens the BOQ. The figures are illustrative.

Illustrative example: bid capacity check (assumed figures; use the formula, multiplier and update factors in your RFP)
InputValueNote
A: updated annual turnoverRs 160 croreBest year of the last five, updated by the RFP's factors (assumed)
N: construction period2 yearsFrom the RFP
M: multiplier2.5Assumed for this example
A x N x MRs 800 crore
B: existing commitmentsRs 470 croreBalance value of works in hand
Available bid capacityRs 330 croreBelow the Rs 350 crore estimate

The firm is Rs 20 crore short. Its options are limited and none is instant: wait until a running contract is closer to completion and B falls, bid with a joint venture partner if the RFP allows one, or pass. It passes on this package, logs the Tender ID, and watches the result to see who won and at what discount, which helps it price the next package on that corridor.

This is the kind of call to make in the first hour, not the last week. A structured bid/no-bid decision saves the estimating team for packages the firm can actually win.

How AI tools help with NHAI tenders, and what your team decides

Highway RFPs are long, and the clauses that matter (capacity, similar work definitions, joint venture rules, change of scope) are spread across the RFP and the draft agreement. AI tools are useful for pulling those clauses into one view with a reference to the source page.

TenderGenie scores opportunities for relevance and extracts qualification criteria from tender packs with source references. It also compares TQ/PQ criteria with your organization's credentials and highlights gaps that need evidence or a partner. See how to evaluate tender eligibility.

Award records help too. TenderGenie adds award history, frequent bidders and pricing signals from available award records as context, and keeps past tenders and approved credentials on hand, so the completion certificates behind a technical capacity claim are easy to find and check.

Your team still owns the numbers. Someone has to decide what counts in B, which past projects meet the similar work definition, whether a joint venture is worth it, and what discount the company can live with. Those are judgment calls with your name on the bid.

Questions and answers

Where can I find NHAI tenders?

NHAI tenders are published on the central eProcurement system at etenders.gov.in. Open Tenders by Organisation and select National Highways Authority of India, or search by keyword such as the highway number or state. The NHAI website also carries tender information, but bids are submitted on the portal with a registered digital signature certificate.

How do I check NHAI tender results?

Note the Tender ID of the package. On etenders.gov.in, Tenders Status shows the stage the tender has reached, and Results of Tenders lets you search by Tender ID or keyword to see the award of contract date and details. Opening summaries show the bidders and, after financial opening, their quoted figures.

Is there an NHAI tender result today list?

No single daily list exists. Results are recorded tender by tender on the portal, so the reliable method is to keep the Tender IDs you care about and check their status after each opening date. News reports and aggregator pages can alert you, but the portal record is what counts.

What is a toll plaza tender?

It is a contract for an agency to collect user fee at an NHAI-operated toll plaza. Instead of quoting a cost, bidders quote the amount they will remit to NHAI, and the highest acceptable remittance usually wins. The agency carries the risk that collections fall short of what it has promised to pay.

What is the difference between EPC and HAM in NHAI tenders?

In EPC, NHAI pays the contractor in stages to design and build the road, and the contractor carries no traffic risk. In the hybrid annuity model, part of the cost is paid during construction and the rest as annuities during operation, so the bidder also arranges financing and maintains the road. HAM RFPs ask for financial capacity too.

How is bid capacity calculated in NHAI tenders?

Highway RFPs usually use a formula of the form A x N x M minus B, where A is updated annual turnover, N is the construction period in years, M is a multiplier set in the RFP and B is the value of existing commitments. The result must be at least the estimated project cost. Always use the exact formula and factors in the RFP.

Can a small contractor bid for NHAI tenders?

Large EPC and HAM packages need bid capacity, similar work experience and net worth that small firms rarely have. Smaller NHAI tenders from regional offices, such as maintenance, repairs and amenities, have lower thresholds. Many small contractors also work as subcontractors to the main contractor before they bid directly.

Sources

  1. Central government eProcurement system (etenders.gov.in), NHAI organization listing and results pages (opens in a new tab)
  2. National Highways Authority of India (opens in a new tab)
  3. NHAI: RFP for user fee collection at Tundla toll plaza (December 2013) (opens in a new tab)
  4. MoRTH: standard documents for EPC, HAM, BOT and TOT (opens in a new tab)

Rules and portal steps change. Check the current tender document and the buyer's portal before you rely on any figure here.

See it on your tender